Texas Wind PowerTexas Wind Power    
PO BOX 684584    
Austin Texas    
78768    

Fax (512) 440-0277    

Projects

Future

Lubbock Wind Program - two Phase

  1. Lubbock Power and Light
    7.5 MW
     3 2.5 MW Turbines
  2. Texas New Mexico Power
    42.5 MW
    17 2.5 MW Turbines

Texas Wind Power has a 20 Wind Turbine 25 year agreement with Lubbock Power and Light. The project is designed in two phases. The first phase is three turbines, planned to be interconnected directly to LP&L's distribution system. The second phase is up to 17 wind turbines dependent on green marketing interests with LP&L customers. Project planned to provide about $10 million in capital investment in Lubbock county by 2010.

Completed

Brazos Wind Ranch™ @ Fluvanna

  • 160 MW
  • Bandera and Scurry County, Texas
  • 160 Mitsubishi 1 MW Turbines
  • Operating December 2003
  • Energy for TXU/Green Mountain Energy
  • Energy for 56,000 households per year

Llano Estacado Wind Ranch™ @ White Deer

  • 80 MW
  • Carson County, Texas
  • 80 Mitsubishi 1 MW Turbines
  • Operating December 2001
  • Energy for Xcel Energy
  • Energy for 28,000 households per year

Hueco Mountain Wind Ranch™ @ El Paso

  • 2 MW
  • El Paso County, Texas
  • 2 Vestas V47 660 kW Turbines
  • Operating April 2001
  • Energy for El Paso Electric
  • Energy for about 750 households per year

King Mountain Wind Ranch™ -Three Separate Phases

  1. Austin Energy
    76 MW
    59 Bonus 1.3 MW Turbines
  2. Texas New Mexico Power
    3 MW
    2 Bonus 1.3 MW Turbines
  3. Reliant Energy
    200 MW 153 Bonus
    1.3 MW Turbines
  • 279 MW total
  • Upton County, Texas
  • Fully operating December 2001
  • Energy for about 97,650 households per year

Woodward Mountain Wind Ranch™

  • 160 MW
  • Pecos County, Texas
  • 242 Vestas V47 660 kW Turbines
  • Operating July 2001
  • Energy to TXU
  • Energy for about 56,000 households per year

Llano Estacado Wind Ranch™ @ Texico

  • 2 MW
  • Curry County, New Mexico
  • 3 Vestas V47 660 kW Turbines
  • Phase 1 operating June 1999
  • Phase 2 operating December 2003
  • Energy for Southwestern Public Service Company
  • Energy for about 700 households per year

Southwest Mesa Wind Farm

  • 75 MW
  • Crockett County, Texas
  • 107 Micon 700 kW Turbines
  • Operating May 1999
  • Energy for CSW
  • Energy for about 26,250 households per year
















PROJECT IMAGES

 

 

Brazos Wind ranch.jpg (6506306 bytes)
Brazos Wind Ranch™
@ Fluvanna
 

 
White Deer Wind Ranch
Llano Estacado Wind Ranch™ @ White Deer
 

 
Heuco Wind Ranch
Hueco Mountain Wind Ranch™ @ El Paso
 

 
King Mountain Wind Ranch
King Mountain Wind Ranch™
 

 
Woodward Wind Ranch
Woodward Mountain Wind Ranch™

 
 
Texico Wind Ranch
Llano Estacado Wind Ranch™ @ Texico
 

 
Southwest Mesa Wind Farm
Southwest Mesa Wind Farm